The draft of the Federal EIS is now out.  Once again, we have the opportunity to submit comments.  We will provide information about this shortly.

The public meetings hosted by the U.S. Department of Agriculture Rural Utilities Service (RUS) for the Cardinal-Hickory Creek 345-kV Transmission Line Project (C-HC Project) Draft Environmental Impact Statement (EIS) have been postponed due to the partial Federal Government shutdown. The cancelled meetings are listed below and will be rescheduled once the Federal Government reopens.

January 24, 2019   Formal Public Meeting on Draft of Federal EIS, Dodgeville Bowl, Dodgeville WI 5-7PM
January 28, 2019   Formal Public Meeting on Draft of Federal EIS, Deer Valley Lodge, Barneveld WI 5-8PM
January 29, 2019   Formal Public Meeting on Draft of Federal EIS, Madison Marriott West, Middleton WI 5-8PM
February 5, 2019   Deadline for Federal EIS comments

 

 

Thanks to everyone who submitted comments to WI Public Service Commission (PSC) regarding the State Environmental Impact Statement (EIS).